TORONTO — Generation Mining Limited (TSX: GENM) (OTCQB: GENMF) (the “Company”) is pleased to provide an update on detailed engineering, procurement and construction readiness activities for its 100%-owned Marathon Copper-Palladium Project (the “Marathon Project” or the “Project”), located on the north shore of Lake Superior in Northwestern Ontario, Canada.
Article content
Early Procurements and Construction Readiness
Article content
In March 2026, the Company appointed Ausenco as the engineering, procurement and construction management partner for the Marathon Project. Subsequent to the appointment, the Company, Ausenco and other consultants (the “EPCM Team”) advanced multiple procurement packages and bid evaluation processes in support of project execution. Bid pricing received to date for major equipment and construction packages represents approximately 30% of the Project’s estimated capital cost. Taken together, the aggregate pricing received for these packages (reflecting both positive and negative variances) is at or below the aggregate corresponding cost allowances included in the Company’s 2025 Feasibility Study. Major equipment and construction packages progressed to date include:
Article content
Bid technical-commercial evaluations have commenced for these packages as part of the procurement and contractor selection process. Commercial reviews and packaging optimization discussions also commenced to support final contracting strategies and contractor selection.
Article content
The Company has an agreement to lease, with an option to purchase, a 263-bed construction camp for use as workforce accommodation during the initial site preparation and construction phase. The Company has de-winterized the camp, with approximately 10% of units currently available. Procurement activities for additional workforce accommodations of approximately 286 beds and an overflow construction camp of approximately 500 beds (a peak total of approximately 786 beds) are progressing, including the receipt and evaluation of bids for the permanent camp construction package and associated catering.
Article content
The Company also continued activities associated with early construction readiness and infrastructure planning, including the selection of an original equipment manufacturer to provide the mining fleet for the Project and ongoing discussions regarding a related maintenance and repair contract for the construction and mining operational phases. The Company also selected a fuel supplier for the Project with the contract to include the establishment of future on-site fuel facilities.
Article content
The Company also continued procurement of the temporary construction powerline with Hydro One, with a take-off agreed to peak at 4MW to support both construction and early commissioning needs, while also advancing its agreement for the permanent powerline to support the full Project requirements. Planning activities related to safety systems, medical facilities, telecommunications, real estate, laydown areas, and mining operations, such as drilling and blasting, also advanced in line with Project needs.
Article content
The EPCM Team has advanced process plant optimization through targeted metallurgical testing, layout improvements, site infrastructure design, construction planning, development of project controls, risk management activities, and ongoing review of execution strategies.
Article content
The EPCM Team also advanced construction execution, including the development of Safety Management Plans, the optimization of earthworks sequencing, and the detailed design of upgrades to the main site access road. Risk review sessions were undertaken to support project readiness and integration of project risks and opportunities into the overall project execution strategy.
Article content
Clinton Swemmer, VP Projects, stated, “Our early procurement results are encouraging. Bid pricing received for packages representing approximately 30% of the Project’s estimated capital cost is, in aggregate, at or below the corresponding aggregate Feasibility Study allowances. While individual package results vary, the combined outcome provides additional confidence in the overall capital cost estimate as we advance detailed engineering and construction readiness activities.”
Article content
The scientific and technical content of this news release has been reviewed and approved by Clinton Swemmer, P.Eng., VP Projects of the Company, and a Qualified Person as defined under National Instrument 43-101 – Standards of Disclosure for Mineral Projects.
Article content
About Generation Mining Limited
Article content
Generation Mining’s (TSX: GENM)
Article content
focus is the development of the Marathon Project, a large undeveloped copper-palladium deposit in Northwestern Ontario. The Feasibility Study (the “Technical Report”) with an effective date of November 1, 2024, estimated a Net Present Value (using a 6% discount rate) of C$1.07 billion, an Internal Rate of Return of 28%, and a 1.9-year payback based on the 3-yr trailing average metal prices at the effective date of the Technical Report. Over the anticipated 13-year mine life, the Marathon Project is expected to produce approximately: 2,161,000 ounces of palladium, 532 million lbs. of copper, 488,000 ounces of platinum, 160,000 ounces of gold and 3,051,000 ounces of silver in payable metals. These production estimates and economic projections are forward-looking statements subject to risks and uncertainties. For more information, please review the Technical Report filed under the Company’s profile at
Article content
and available on the Company’s website at
Article content
Forward-Looking Information
Article content
This news release contains certain forward-looking information and forward-looking statements, as defined in applicable securities laws (collectively referred to herein as “forward-looking statements”). Forward-looking statements reflect current expectations or beliefs regarding future events or the Company’s future performance. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “continues”, “forecasts”, “projects”, “predicts”, “intends”, “anticipates”, “targets” or “believes”, or variations of, or the negatives of, such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will” be taken, occur or be achieved, including statements relating to the results of the Company’s procurement and tendering process, the timing and outcome of remaining bid evaluations and contractor selection, the timing of execution of definitive agreements for the mining fleet (including related maintenance), fuel supply and powerline arrangements described herein, the procurement of the permanent camp, the timing of a construction decision, and the anticipated advancement of the Company’s Marathon Project.